Ashpark Primary School — Boiler & Flue Renewal

Renewal of the boiler plant and flue serving a live primary school — ageing boilers replaced with a cascade of high-efficiency condensing boilers and a new flue, backed by pumps, pressurisation, expansion and controls, commissioned and certified by our own mechanical team.

Home/Case Studies/Ashpark Primary School — Boiler & Flue Renewal

The brief

Ashpark Primary School's boiler plant and flue had reached the end of their working life. The brief was a full renewal — strip out the ageing boilers and flue and replace them with a modern, efficient and resilient installation, built around a cascade of condensing boilers rather than a single large unit. That gives the school high efficiency across a wide load range and built-in redundancy, installed to current standards and handed over fully documented, all sequenced around the school.

What we delivered

Stein Group's mechanical team renewed the boiler plant with a cascade of high-efficiency wall-hung condensing boilers and installed a new flue system to suit. The boilers feed a low-loss header that separates the boiler and system circuits cleanly; a Grundfos pump set circulates the heating, a packaged pressurisation unit and expansion vessels hold the system stable, and an L-TEC control panel sequences the plant for efficient, staged operation.

New flue, gas train and system pipework were installed and tested throughout, and the plant room was set out as a clean, logical, maintainable installation — then commissioned and certified so the school inherited a fully evidenced boiler and flue renewal.

Disciplines self-delivered

Mechanical / heating Condensing boiler cascade New flue system Pumps & low-loss header Pressurisation & expansion Controls (L-TEC) Commissioning & certification

The outcome

An efficient, resilient boiler and flue installation for the school — a modulating boiler cascade that turns down to match demand and keeps heating available even if one boiler is offline, on a new compliant flue, backed by clean pump, pressurisation and control arrangements. Fully commissioned, certified and ready to be maintained and evidenced by Stein's own maintenance team.

More work

See the rest of the portfolio.

One partner for the whole building lifecycle.

Design, installation, maintenance and compliance — self-delivered, accountable, and evidenced across your entire estate. Let's talk.

Call 01698 480808 Request a Callback